A. Step by Step guide for construction
Stage |
Key Steps |
Description of Tasks |
Timeline Estimate |
1. Project Concept & Feasibility |
Feasibility Study |
Assess site, demand, budget, and legal requirements |
1-2 months |
Budget Estimation |
Initial cost estimation, financing, approvals |
|
|
Site Selection |
Land procurement, accessibility, zoning compliance |
|
|
2. Design & Planning |
Appointment of Architects & Consultants |
Hire architect, structural engineer, MEP consultant, landscape consultant |
2-4 months |
Conceptual Design |
Prepare preliminary layout, floor plans, 3D visualizations |
|
|
Detailed Design & Drawings |
Structural, architectural, electrical, plumbing, HVAC, fire safety, landscape, façade |
|
|
Environmental & Government Approvals |
Fire NOC, environmental clearance, local authority approvals |
|
|
3. Tendering & Contractor Selection |
Preparation of Tender Documents |
BOQ, technical specifications, RFP preparation |
1-2 months |
Tender Floating & Evaluation |
Invite bids, evaluate technical & financial proposals |
|
|
Contract Signing |
Award contract, finalize payment schedule, mobilization advance |
|
|
4. Site Preparation & Initial Works |
Site Clearance & Levelling |
Remove debris, tree cutting, grading |
1 month |
Soil Testing & Survey |
Geotechnical tests, topographic survey |
|
|
Temporary Site Setup |
Site office, storage, labor camps, safety measures |
|
|
5. Foundation & Substructure |
Excavation & Earthwork |
Digging for foundation and basement (if applicable) |
2-3 months |
Foundation Construction |
Piling, footing, plinth beam |
|
|
Waterproofing & Basement Work |
Underground tank, sump pits, drainage |
|
|
6. Superstructure (Frame & Walls) |
RCC/Steel Frame Erection |
Column, beam, slab casting (floor-wise) |
4-6 months |
Masonry & Partition Walls |
Brick/block work for walls, plastering |
|
|
7. Mechanical, Electrical & Plumbing (MEP) Works |
Electrical & HVAC Installation |
Wiring, ducting, transformers, panels |
4-6 months (parallel) |
Plumbing & Firefighting |
Water supply, drainage, fire suppression systems |
|
|
IT & Networking |
CCTV, access control, data cabling |
|
|
8. Exterior & Interior Finishing |
Flooring & Tiling |
Marble, tiles, wood flooring |
3-5 months |
False Ceiling & Paint |
Interior & exterior finishes |
|
|
Façade & Window Installation |
Glass, aluminum cladding, doors & windows |
|
|
9. External Development & Landscaping |
Paving & Parking |
Driveways, parking areas, signage |
1-2 months |
Green Spaces & Street Furniture |
Lawns, gardens, fountains, seating areas |
|
|
10. Testing, Inspection & Handover |
Quality Testing |
Structural integrity, water & electrical tests |
1-2 months |
Authority Approvals |
Fire safety, occupancy certificate, municipal clearance |
|
|
Final Handover |
System commissioning, training, facility management setup |
|
Stage |
Drawing Type (Technical Name) |
Purpose & Description |
Concept & Planning |
Conceptual Drawings |
Rough sketches to visualize design ideas and spatial planning |
Site Plan |
Shows the building’s location, roads, landscape, and site boundaries |
|
Zoning & Compliance Drawings |
Ensures adherence to building laws, setbacks, and height restrictions |
|
Design Development |
Floor Plan |
A top-down view showing the layout of rooms, walls, and circulation spaces |
Elevation Drawings |
Front, side, and rear views showing the external appearance |
|
Section Drawings |
Vertical cut-through of the building showing internal details |
|
3D Perspective Views |
Rendered images to visualize the final design realistically |
|
Approval & Tendering |
Approval Drawings |
Submitted to authorities for obtaining building permissions |
Fire & Safety Drawings |
Includes fire exits, sprinkler systems, and safety features |
|
Tender Drawings |
Used for bidding and contractor selection, includes material specifications |
|
Execution & Construction |
Good for Construction (GFC) Drawings |
Finalized, detailed drawings used on-site for execution |
Shop Drawings |
Highly detailed drawings for fabrication (e.g., doors, windows, joinery) |
|
As-Built Drawings |
Records the exact work executed, including any on-site modifications |
Drawing Type |
Technical Name |
Key Features & Differences |
Building Layout |
Floor Plan |
Top view showing rooms, walls, doors, and windows |
Exterior Appearance |
Elevation Drawing |
Flat 2D view showing building’s façade from different angles |
Internal Sections |
Section Drawing |
Vertical cut-through to show internal structure, ceiling height, and materials |
Detailed Construction |
Working Drawing |
Highly detailed technical drawing for builders and engineers |
Electrical Layout |
Electrical Plan |
Placement of switches, lights, and power outlets |
Plumbing System |
Plumbing & Drainage Plan |
Shows water supply, drainage pipes, and fittings |
Fire Safety |
Fire Evacuation Plan |
Emergency exits, hydrants, sprinklers, and alarms |
HVAC Layout |
Mechanical Drawings |
Ductwork, ventilation, and air conditioning layout |
Category |
GFC Drawing Type |
Purpose |
Architectural |
Floor Plans |
Shows room layout, doors, windows, and circulation |
Elevations |
External view of the building from all sides |
|
Sections |
Vertical cuts showing internal details like ceiling heights, walls, and materials |
|
Staircase Details |
Design, riser/tread dimensions, and railing details |
|
Structural |
Foundation Plan |
Shows footings, columns, and reinforcement details |
Column Layout |
Positions and sizes of structural columns |
|
Slab & Beam Layout |
Placement of beams, slabs, and reinforcement details |
|
MEP (Mechanical, Electrical, Plumbing) |
Electrical Layout |
Wiring, lighting, switchboards, and power sockets |
Plumbing Layout |
Water supply, drainage, and pipe routes |
|
HVAC Plan |
Ducting, ventilation, and air conditioning systems |
|
Fire & Safety |
Fire Evacuation Plan |
Fire exits, sprinklers, smoke detectors |
Firefighting System |
Hydrants, extinguishers, and alarm systems |
|
Landscaping & Site Work |
Site Plan |
Roads, parking, green spaces, and pathways |
Boundary Wall Details |
Dimensions and materials of the compound wall |
Stage |
Element |
Test Name |
Purpose (Why is it needed?) |
Who Conducts It? |
Material for PDI & What is Checked? |
1. Pre-Construction |
Soil |
Soil Bearing Capacity (SBC) Test |
Checks if soil can bear the building load. |
Geotechnical Engineer |
- |
|
Soil Compaction Test |
Ensures soil is compacted to prevent settlement. |
Site Engineer |
- |
|
Water |
pH & Chemical Test |
Ensures water quality for concrete mixing. |
Testing Lab |
- |
|
2. Foundation & Structural Work |
Concrete |
Slump Test |
Checks concrete workability before pouring. |
Site Engineer |
- |
|
Cube Compression Test |
Ensures concrete strength after curing. |
Testing Lab |
- |
|
Steel |
Tensile Strength Test |
Ensures steel reinforcement can bear load. |
Manufacturer/Testing Lab |
Steel Bars – Diameter, strength, bendability, rust-free surface |
|
Bricks |
Compressive Strength Test |
Ensures bricks can handle load without cracking. |
Site Engineer |
Bricks – Size, shape, strength, water absorption |
|
3. Superstructure Work |
Plaster |
Adhesion Test |
Ensures plaster sticks well to walls. |
Site Engineer |
- |
Flooring/Tiles |
Water Absorption Test |
Prevents tile breakage due to water absorption. |
Manufacturer/Site Engineer |
Tiles & Stone Slabs – Dimensions, cracks, polish, water absorption |
|
4. MEP (Mechanical, Electrical, Plumbing) Work |
Plumbing |
Pressure Test |
Checks pipes for leaks under pressure. |
Plumber/Site Engineer |
Pipes & Fittings – Thickness, material quality, leak-proof joints |
Electrical |
Insulation Resistance Test |
Ensures electrical wiring is safe. |
Electrical Engineer |
Cables & Switches – Wire gauge, insulation, conductor quality |
|
HVAC |
Air Leakage Test |
Prevents energy loss in ducting. |
HVAC Contractor |
Ducting Material – Thickness, leakage, insulation quality |
|
5. Finishing Stage |
Paint |
Adhesion & Thickness Test |
Ensures paint is applied properly and evenly. |
Paint Contractor |
- |
Glass |
Impact & Toughness Test |
Checks if glass can handle impacts safely. |
Manufacturer |
Glass Panels – Strength, thickness, edge polishing |
|
Waterproofing |
Ponding Test |
Checks waterproofing before final finishes. |
Waterproofing Contractor |
- |
|
6. Post-Construction & Final Testing |
Building |
Structural Load Test |
Ensures building can handle expected loads. |
Structural Engineer |
- |
Fire Safety |
Fire Hydrant Flow Test |
Ensures fire hydrants provide enough pressure. |
Fire Safety Officer |
Fire Safety Equipment – Pressure, flow rate, functionality |
|
Elevators |
Lift Load Test |
Checks if lifts can handle the rated load. |
Elevator Contractor |
Elevators & Lift Components – Load-bearing capacity, safety mec |
Task ID |
Activity |
Predecessor(s) |
Duration |
A |
Site Preparation & Earthwork |
None |
10 |
B |
Foundation Work (Excavation, PCC, Footing, Plinth Beam) |
A |
20 |
C |
Ground Floor Columns & Beams |
B |
15 |
D |
Ground Floor Slab Casting (Shuttering, Reinforcement, Concrete) |
C |
10 |
E |
First Floor Columns & Beams |
D |
15 |
F |
First Floor Slab Casting (Shuttering, Reinforcement, Concrete) |
E |
10 |
G |
Ground Floor Brickwork & Partition Walls |
D |
25 |
H |
First Floor Brickwork & Partition Walls |
F |
25 |
I |
Plastering & Waterproofing |
G, H |
15 |
J |
Electrical & Plumbing (Conduits & Pipes) |
G, H |
20 |
K |
Flooring & Tiling |
I, J |
20 |
L |
Painting & Finishing |
K |
15 |
M |
External Works (Landscaping, Parking, Boundary Wall) |
L |
10 |
N |
Final Testing & Handover |
M |
10 |
To reduce the project duration from 175 days to ~125 days, consider the following time-saving strategies:
1. Parallel Execution of Tasks
- Start First Floor Columns before Ground Floor Brickwork is fully completed.
- Begin Plastering on the Ground Floor while First Floor Brickwork is ongoing.
- Execute Electrical and Plumbing work alongside Plastering instead of waiting for it to finish.
2. Use Precast Components
- Use precast slabs, lintels, and stairs instead of casting them on-site.
- This eliminates curing time delays and speeds up construction by 10-12 days.
3. Use High-Performance Concrete (HPC) & Ready-Mix Concrete (RMC)
- HPC has faster curing times, allowing slab and column work to move ahead 5-7 days faster.
- RMC avoids on-site mixing delays, reducing 5-6 days.
4. Efficient Shuttering Techniques
- Use Mivan or aluminum formwork for slab casting, which speeds up formwork removal.
- Saves 7-10 days in overall structure work.
5. Deploy Multiple Work Crews
- Parallel teams for flooring, painting, and finishing can save 10-12 days.
- Specialized teams for electrical and plumbing work allow work to move simultaneously with plastering.
6. Efficient Procurement & Logistics Planning
- Ensure no material shortages that could cause work stoppages.
- Saves 5-7 days by preventing delays in procurement.
category |
Role |
Purpose / Responsibilities |
Estimated Manpower |
Management & Planning |
Project Manager |
Oversees the entire project, manages resources, timeline, and coordination. |
1-2 |
Site Engineer |
Supervises on-site work, quality control, and compliance with design. |
2-3 |
|
Architect |
Designs the building layout, aesthetics, and usability. |
1 |
|
Structural Engineer |
Ensures stability, load-bearing capacity, and structural integrity. |
1 |
|
Quantity Surveyor |
Estimates material requirements, cost control, and billing. |
1 |
|
Safety Officer |
Ensures compliance with safety norms and reduces site hazards. |
1 |
|
Procurement Manager |
Manages purchase and supply of construction materials. |
1 |
|
Civil & Structural Works |
Masons |
Constructs brickwork, plastering, and finishing works. |
30-40 |
Carpenters |
Builds formwork for concrete slabs, beams, and columns. |
15-20 |
|
Steel Fixers (Bar Benders) |
Cuts, bends, and fixes steel reinforcement for RCC work. |
10-15 |
|
Concrete Workers |
Mixes, pours, and levels concrete. |
15-20 |
|
Scaffolding Workers |
Installs and maintains scaffolding for safe work at height. |
5-10 |
|
General Laborers (Helpers) |
Assists in carrying materials, mixing cement, and general site activities. |
40-50 |
|
Mechanical, Electrical & Plumbing (MEP) |
Electricians |
Installs wiring, lighting, and electrical systems. |
10-15 |
Plumbers |
Installs water supply, drainage, and sanitation systems. |
10-12 |
|
HVAC Technicians |
Installs heating, ventilation, and air conditioning (if applicable). |
5-7 |
|
Lift Technicians |
Installs and maintains elevators (if applicable). |
2-3 |
|
Finishing & Interiors |
Painters |
Applies paint, polishes, and surface finishes. |
10-15 |
Tile & Marble Layers |
Installs flooring, wall tiles, and marble surfaces. |
10-15 |
|
False Ceiling Workers |
Installs false ceilings and gypsum board partitions. |
5-10 |
|
Glass & Aluminium Workers |
Installs windows, doors, and glass facades. |
5-10 |
|
Interior Decorators |
Designs and installs interior furnishings and lighting. |
3-5 |
|
External & Landscaping |
Pavers & Road Workers |
Lays external pavements, driveways, and pathways. |
5-10 |
Gardeners (Landscapers) |
Plants trees, maintains green areas, and landscaping. |
3-5 |
|
Gate & Boundary Workers |
Constructs fences, gates, and boundary walls. |
5-7 |
|
Security & Support |
Security Guards |
Ensures site safety and material security. |
5-7 |
Cleaning Staff |
Keeps the site clean and removes construction debris. |
3-5 |
|
Total Manpower Requirement |
- |
At peak stage: 150-200 workers |
150-200 |
Component |
Description |
Function |
Sub-Parts |
Types |
Foundation |
The lowest part of the building structure, set in the ground. |
Provides stability, distributes the load to the soil, and prevents settling. |
Footings, Piles, Grade Beams |
Shallow (e.g., Spread Footing), Deep (e.g., Pile Foundation) |
Plinth |
The portion between the foundation and the ground floor. |
Prevents moisture from entering the building and raises the structure above ground level. |
Plinth Beam, Damp Proof Course (DPC) |
Low Plinth, High Plinth |
Columns |
Vertical structural elements supporting the building. |
Transfers the load from the slab and beams to the foundation. |
Reinforcement, Formwork, Concrete Cover |
RCC Columns, Steel Columns, Composite Columns |
Beams |
Horizontal load-bearing elements. |
Transfers load from slabs to columns, preventing excessive bending. |
Reinforcement, Stirrups, Concrete Cover |
Simply Supported, Cantilever, Continuous |
Slab |
Flat structural component forming the floors and ceilings. |
Supports the load of occupants and furniture, providing separation between floors. |
Reinforcement, Concrete, Shuttering |
One-Way Slab, Two-Way Slab, Flat Slab |
Walls |
Vertical enclosures that provide security and support. |
Separates spaces, bears loads (in some cases), and provides insulation. |
Brickwork, Reinforcement (for RCC Walls), Plaster |
Load-Bearing Walls, Partition Walls, Shear Walls |
Roof |
Top covering of a building structure. |
Protects from weather conditions and provides insulation. |
Trusses, Rafters, Purlins, Roofing Sheets |
Flat Roof, Pitched Roof, Shell Roof |
Doors |
Openings that allow entry and exit from rooms and buildings. |
Provides access and security. |
Frame, Shutters, Hinges, Locks |
Wooden, Metal, Glass, uPVC |
Windows |
Openings in walls allowing ventilation and light. |
Provides air circulation, light, and visibility. |
Frame, Glass, Shutters |
Casement, Sliding, Fixed, Louvered |
Staircase |
Vertical circulation system consisting of steps. |
Provides access between different floors. |
Steps, Landings, Handrails, Balusters |
Straight, Spiral, Dog-Legged, Open-Well |
Flooring |
The surface of a room on which people walk. |
Provides a durable and aesthetic walking surface. |
Subfloor, Finishing Layer, Skirting |
Tile, Marble, Wooden, Concrete |
Ceiling |
Overhead surface inside a building. |
Conceals structural elements and enhances aesthetics. |
False Ceiling, Decorative Elements |
Plasterboard, POP, Wooden, Metal |
Electrical System |
Network of wiring and fixtures supplying power. |
Provides electricity for lighting, appliances, and safety. |
Wiring, Switches, MCBs, Distribution Boards |
Surface Wiring, Concealed Wiring |
Plumbing System |
Water supply and drainage network. |
Supplies clean water and removes wastewater. |
Pipes, Valves, Fittings, Water Tanks |
UPVC, CPVC, PPR, GI |
HVAC System |
Heating, Ventilation, and Air Conditioning setup. |
Regulates indoor temperature, humidity, and air quality. |
Ducts, Vents, Compressors |
Split AC, Centralized, VRF |
Fire Safety System |
Fire prevention and suppression system. |
Detects and controls fires, ensuring safety. |
Fire Extinguishers, Sprinklers, Smoke Detectors |
Manual, Automatic |
Paint & Finishing |
Coating applied to walls, ceilings, and other surfaces. |
Enhances aesthetics and protects surfaces from damage. |
Primer, Paint, Putty |
Water-Based, Oil-Based, Textured |
This comment has been removed by the author.
ReplyDeleteUK buyers looking for durable HDPE should check this out. Their HDPE sheet UK selection is pretty solid with export options. HDPE sheet UK covers multiple thicknesses and uses, from packaging to lining.
ReplyDeletehi
ReplyDeleteTorn between POP and gypsum for your false ceiling? Learn about their differences, installation advantages, and design possibilities to decide what is best for your home.
ReplyDeletePOP vs Gypsum False Ceilings: A Complete Comparison
False ceilings add to the aesthetic appeal while concealing wiring and ducts. Let's see how POP and gypsum compare
Both POP and gypsum possess distinct benefits based on your intended design. At Quartier Studio, we assist homeowners in choosing the ideal false ceiling material for durability, beauty, and functionality.
Read More:- https://quartierinterior.com/pop-and-gypsum-false-ceiling/
Great post on building construction basics! Very informative for piling contractors and construction professionals looking to strengthen foundational knowledge. Thanks for sharing!
ReplyDeletehttps://advancedqualitycentre.blogspot.com/2022/07/steel-making-process.html?sc=1751539261233
ReplyDeleteUnderstanding each phase of building helps a lot when looking for the best construction services. Thanks for explaining it in such a simple way.
ReplyDeleteThis breakdown makes it easier to understand what to expect from experienced commercial builders during a project. Good to see it explained step by step.
ReplyDelete