A. Step by step guide for road construction
Step No. |
Activity |
Details |
1 |
Project Planning & Feasibility Study |
Identify the road stretch, assess existing conditions, conduct traffic analysis, and perform soil investigation & topographical surveys. |
2 |
Preparation of Detailed Project Report (DPR) |
Includes road width, pavement type, utility plans, drainage, lighting, smart elements, and cost estimates. |
3 |
Preparation of Detailed Drawings & Approvals |
Obtain necessary approvals for road cross-sections, utility duct layouts, drainage plans, lighting, and landscape designs. |
4 |
Shifting of Existing Utilities |
Relocate underground water pipelines, electricity cables, telecom ducts, and sewage lines to prevent conflicts. |
5 |
Site Clearance & Marking |
Remove encroachments, debris, and existing damaged pavement. Mark road alignment and positions for smart elements. |
6 |
Excavation & Preparation of Subgrade |
Excavate to required depth and compact the subgrade. Lay geo-textile fabric (if needed) for soil stabilization. |
7 |
Stormwater Drainage Construction |
Construct side drains, culverts, and underground stormwater drainage channels to prevent waterlogging. |
8 |
Laying of Utility Ducts |
Install underground ducts for electricity, telecom, gas, fiber optic cables, and water supply with maintenance access points. |
9 |
Base Layer Construction |
Lay Granular Sub-Base (GSB) followed by Wet Mix Macadam (WMM) for road stability, ensuring proper compaction. |
10 |
Pavement Construction |
Based on road type: bituminous or concrete |
11 |
Footpath & Pedestrian Infrastructure |
Construct footpaths using interlocking tiles/concrete, install tactile paving for visually impaired, and develop pedestrian-friendly walkways. |
12 |
Smart Elements Installation |
Install smart poles, LED streetlights, CCTV cameras, traffic signals, smart parking sensors, EV charging stations, and integrate Wi-Fi & IoT-based monitoring. |
13 |
Horticulture & Green Cover Development |
Develop green belts, plant native trees, install tree guards, vertical gardens, and landscape the medians and footpaths. |
14 |
Signage & Road Markings |
Install traffic signboards, zebra crossings, lane markings, reflective studs, and digital traffic information systems for safety. |
15 |
Final Inspection & Quality Check |
Conduct a thorough quality audit, check pavement smoothness, utility ducts, smart installations, and ensure stormwater drainage efficiency. |
16 |
Commissioning & Handover |
Open the road for public use, conduct final inspections, rectify defects, integrate smart monitoring systems, and complete project documentation. |
Drawing Name |
Purpose |
Details Included |
Topographic Survey & Existing Utility Plan |
To assess existing land conditions and identify existing utilities. |
Road width, contours, slopes, existing utilities (water, electricity, telecom, sewer), trees, encroachments. |
Alignment & Cross-Section Drawing |
Defines road alignment and width, ensuring compliance with road design standards. |
Road width, lanes, shoulders, footpath, cycle tracks, median, ROW (Right of Way). |
Soil Investigation & Subgrade Preparation Plan |
Helps in designing the base and sub-base layers of the road. |
Soil type, bearing capacity, excavation depth, compaction details, stabilization layers (if required). |
Stormwater Drainage Plan |
Ensures proper water drainage to prevent flooding and waterlogging. |
Location of stormwater drains, slopes, manholes, outfalls, rainwater harvesting pits. |
Utility Duct Layout Plan |
Ensures organized placement of underground utilities without conflicts. |
Positions of ducts for electricity, water, sewage, telecom, fiber optics, and gas pipelines. |
Pavement Layer Composition & Structural Design |
Determines the road strength and durability. |
Road base, sub-base, bituminous/concrete layer details, thickness, and material specifications. |
Road Profile & Longitudinal Section |
Shows elevation variations along the road length. |
Gradient, elevation, slope details, and cut-and-fill requirements. |
Bituminous/Concrete Pavement Design Details |
Ensures proper material and layer design for road longevity. |
Type of pavement, thickness of each layer, material composition, reinforcement details (for concrete roads). |
Footpath & Pedestrian Infrastructure Plan |
Ensures safe and accessible pedestrian movement. |
Width of footpaths, material details, tactile paving for visually impaired, ramps, street furniture locations. |
Smart Infrastructure & Electrical Plan |
Placement of smart elements and electrical systems. |
Streetlights, smart poles, CCTV locations, Wi-Fi hotspots, traffic signals, EV charging stations. |
Horticulture & Landscaping Plan |
Defines green spaces for aesthetics and environmental benefits. |
Locations of trees, shrubs, planters, green medians, vertical gardens, and irrigation system. |
Signage & Road Marking Plan |
Enhances road safety and visibility for users. |
Traffic signs, zebra crossings, lane markings, speed limits, direction boards, reflective studs. |
Junction & Traffic Management Plan |
Improves traffic flow and safety at intersections. |
Roundabouts, signals, pedestrian crossings, traffic islands, lane bifurcations. |
Final As-Built Drawings |
Document actual execution and any modifications made. |
Final layouts, changes made during construction, approved modifications, and location of all underground utilities. |
Stage |
Essential Test |
Purpose |
Conducted By |
1. Soil/Subgrade Preparation |
CBR Test (California Bearing Ratio) |
Checks soil strength for load-bearing capacity. |
Geotechnical Engineer / Third-Party Lab |
|
Soil Compaction Test (Field Dry Density Test) |
Ensures proper soil compaction for stability. |
Contractor QC Team / Site Engineer |
2. Base & Sub-Base (GSB, WMM, etc.) |
Aggregate Impact Value Test |
Ensures aggregates are strong and durable. |
Site Engineer / Third-Party Lab |
|
Gradation Test |
Confirms correct particle size distribution for base layers. |
Contractor QC Team |
3. Bituminous Road Work |
Bitumen Content Test |
Ensures correct bitumen percentage in the mix. |
Third-Party Lab / Asphalt Plant |
|
Marshall Stability Test |
Checks strength and stability of bituminous mix. |
Government / Private Testing Lab |
|
Core Cutting Test |
Confirms the thickness of the laid bituminous layer. |
Third-Party Lab |
4. Concrete Road (If applicable) |
Slump Test |
Checks workability of concrete before laying. |
Site Engineer / Contractor |
|
Cube Strength Test |
Ensures concrete attains required strength. |
Third-Party Testing Lab |
5. Final Road Quality Check |
Benkelman Beam Deflection Test |
Measures the structural strength of the pavement. |
Government / Third-Party Testing Agency |
|
Pavement Roughness Test (IRI – International Roughness Index) |
Ensures smooth driving surface. |
Specialized Survey Agency |
Component |
Test Name |
Purpose |
Stage of Testing |
Drain Construction |
Concrete Strength Test (Cube Test) |
Ensures required strength of RCC drains. |
After 7, 14, and 28 days of casting |
Water Permeability Test |
Checks for water leakage or seepage. |
After curing of concrete |
|
Gradient & Flow Test |
Ensures proper drainage slope and water flow. |
After construction, before road laying |
|
Utility Ducts |
Compaction Test for Backfilling |
Ensures soil compaction around ducts. |
After backfilling of trenches |
Air Pressure Test (for conduits) |
Checks for air-tightness of electrical and telecom conduits. |
Before cable installation |
|
Water Flow Test (for water lines) |
Ensures proper water supply and pressure in pipes. |
After pipe installation, before covering |
|
Street Lights |
Earth Resistance Test |
Ensures proper earthing for safety. |
Before energizing the system |
Illumination Level Test (Lux Test) |
Checks if lighting meets required brightness levels. |
After installation, during night testing |
|
Pole Load Test |
Ensures pole can withstand wind and load conditions. |
Before pole erection |
|
Footpath & Pavement |
Compressive Strength Test (for paver blocks) |
Ensures durability of footpath paver blocks. |
Before installation |
Skid Resistance Test |
Ensures anti-slip properties of footpath surface. |
After completion |
|
Signages & Road Markings |
Retro-Reflectivity Test |
Ensures visibility of road signs and markings at night. |
After application |
Stormwater Management |
Percolation Test (for rainwater harvesting pits) |
Checks ground absorption capacity. |
Before constructing pits |
Item |
Why is PDI Required? |
When to Conduct PDI? |
Who Conducts It? |
Street Light Poles & Fixtures |
Ensures proper fabrication, height, alignment, and wiring. |
Before dispatch from manufacturer. |
Vendor + Project QC Team |
LED Street Lights |
Checks wattage, lumens, material quality, and IP rating. |
Before dispatch. |
Vendor + Electrical Engineer |
Utility Duct Pipes (HDPE/PVC/GI) |
Ensures correct diameter, material thickness, and strength. |
Before dispatch. |
Vendor + Site Engineer |
Precast RCC Drain Covers |
Verifies dimensions, strength, and load-bearing capacity. |
Before dispatch. |
Vendor + Structural Engineer |
Paver Blocks for Footpath |
Checks compressive strength, uniformity, and anti-skid properties. |
Before dispatch. |
Vendor + Quality Inspector |
Signboards & Road Markings Paint |
Ensures retro-reflectivity, durability, and compliance with IRC standards. |
Before dispatch. |
Vendor + Traffic Engineer |
Smart Road Furniture (Benches, Bollards, Railings) |
Ensures correct material, finish, and durability. |
Before dispatch. |
|
Layer |
Purpose |
Material Used |
Applicable to |
1. Subgrade |
Acts as the foundation of the road, bearing the load of traffic. |
Compacted natural soil, sand, geotextiles (if needed for stabilization). |
All roads (bituminous & concrete) |
2. Granular Sub-Base (GSB) |
Provides drainage and distributes load evenly. |
Crushed stone, gravel, sand, fly ash (in some cases). |
All roads |
3. Base Course (WMM/WBM) |
Provides structural strength to the road. |
- WMM (Wet Mix Macadam): Crushed aggregates, stone dust, water. - WBM (Water Bound Macadam): Aggregates bound with water and compacted. |
All roads |
4. Binder Course (For Bituminous Roads) |
Intermediate layer to bind base and surface course. |
- Bituminous Macadam (BM): Coarse aggregates mixed with bitumen. - Dense Bituminous Macadam (DBM): Stronger bituminous mix. |
Bituminous roads only |
5. Surface Course (Wearing Layer) |
Provides a smooth, durable surface for vehicles. |
- Bituminous Roads: Bituminous Concrete (BC), Mastic Asphalt. - Concrete Roads: Pavement Quality Concrete (PQC) with reinforcement. |
|
|
|
|
|
Step |
Activity |
Description |
Tentative Time |
1. Marking & Excavation |
Mark trench alignment & dig as per depth |
Done as per design considering future utilities. |
3-5 days |
2. Base Preparation |
Leveling and compacting base |
Ensures stability and prevents settlement. |
1-2 days |
3. Duct Installation |
Laying RCC/PVC pipes or pre-cast ducts |
Placing conduits for electrical, telecom, water, etc. |
5-7 days |
4. Manhole & Chamber Construction |
Creating access points at intervals |
Manholes allow maintenance & future expansion. |
4-5 days |
5. Covering & Backfilling |
Concrete encasement & refilling trench |
Protects ducts and restores surface. |
3-4 days |
6. Surface Restoration |
Rebuilding footpath or road surface |
Final finishing depending on surface type. |
4-6 days |
Step |
Activity |
Description |
Tentative Time |
1. Marking & Excavation |
Layout alignment & digging |
As per design & required depth. |
3-5 days |
2. Base Preparation |
Leveling & compacting base |
Ensures proper gradient for water flow. |
2-3 days |
3. Formwork & Reinforcement |
Placing steel reinforcement (if RCC drain) |
Required for concrete drains to enhance durability. |
4-6 days |
4. Drain Casting (RCC/Masonry) |
Concrete pouring or brick masonry |
Constructing the drain walls & base. |
5-7 days |
5. Curing & Strength Gain |
Allow concrete to gain strength |
Essential for durability & crack prevention. |
7-10 days |
6. Cover Slab/Grating Fixing |
Placing RCC or iron grates |
Protects drain & allows easy cleaning. |
3-4 days |
7. Surface Restoration |
Rebuilding footpath/road if required |
Final finishing work. |
3-5 days |
Step |
Activity |
Description |
Tentative Time |
1. Site Preparation & Excavation |
Clearing, marking, and excavation |
Removal of obstructions, grading, and preparation of the site. |
5-7 days |
2. Subgrade Preparation |
Compaction of natural soil |
Stabilizing the soil base to prevent settlement. |
3-5 days |
3. Sub-Base Layer (GSB - Granular Sub-Base) |
Laying crushed aggregates and compacting |
Ensures load distribution and drainage. |
4-6 days |
4. Base Layer (WMM/WBM) |
Laying Wet Mix Macadam (WMM) or Water Bound Macadam (WBM) |
Provides structural strength. |
5-7 days |
5. Binder Course (For Bituminous Roads) |
Applying Bituminous Macadam (BM) or Dense Bituminous Macadam (DBM) |
Acts as an intermediate layer to bind the base and surface. |
4-6 days |
6. Surface Course (Wearing Layer) |
Laying Bituminous Concrete (BC) or Pavement Quality Concrete (PQC) |
Final smooth surface for vehicles. |
4-6 days |
7. Curing (For Concrete Roads Only) |
Allowing concrete to gain strength |
Essential for durability and preventing cracks. |
7-14 days (if PQC) |
8. Road Marking & Signage Installation |
Painting lane markings, placing road signs |
Enhances safety and traffic management. |
2-4 days |
9. Final Inspection & Opening to Traffic |
Checking quality and final approvals |
Ensuring proper construction before opening. |
1-2 days |
Step |
Activity |
Description |
Tentative Time |
1. Site Survey & Design Planning |
Identifying pole locations and preparing the layout |
Ensures optimal light coverage and alignment with road design. |
2-3 days |
2. Excavation for Pole Foundation |
Digging pits for pole installation |
Depth depends on pole height and wind load. |
2-4 days |
3. Foundation Construction |
Laying concrete foundation for stability |
Ensures pole strength and durability. |
4-6 days |
4. Pole Erection & Alignment |
Installing poles and aligning them properly |
Ensures uniform height and positioning. |
3-5 days |
5. Cable Laying & Ducting |
Placing underground cables for power supply |
Done through pre-installed ducts or new trenches. |
5-7 days |
6. Fixing Electrical Components |
Installing junction boxes, control panels, and switches |
Ensures power regulation and control. |
3-5 days |
7. Light Fixture Installation |
Fixing LED lights, brackets, and fittings |
Mounting the lighting system on poles. |
2-4 days |
8. Connection & Testing |
Connecting to the power supply and checking functionality |
Ensures proper illumination and safety compliance. |
3-5 days |
9. Final Inspection & Commissioning |
Checking alignment, brightness, and system efficiency |
Ensures smooth operation before handover. |
2-3 days |
Task Name |
Duration (Days) |
Dependency (Must be Completed Before Starting) |
Survey & Design |
15 |
None |
Utility Shifting Planning |
10 |
Survey & Design |
Excavation for Ducts (Electric, Water, Telecom) |
20 |
Utility Shifting Planning |
Laying Electrical & Water Pipelines |
25 |
Excavation for Ducts |
Telecom & OFC Laying |
15 |
Excavation for Ducts |
Backfilling & Surface Restoration |
20 |
Laying Electrical & Water Pipelines, Telecom & OFC Laying |
Road Widening & Sub-base Preparation |
25 |
Backfilling & Surface Restoration |
Drainage & Footpath Construction |
20 |
Road Widening & Sub-base Preparation |
Asphalt/Paver Road Surfacing |
15 |
Drainage & Footpath Construction |
Smart Features Installation (Lights, Signage) |
10 |
Asphalt/Paver Road Surfacing |
Final Road Markings & Testing |
7 |
Smart Features Installation |
Project Handover |
5 |
Final Road Markings & Testing |
Category |
Optimized Strategy |
Expected Time Savings |
1. Parallel Execution of Tasks |
Start utility shifting and excavation simultaneously instead of sequentially. |
Saves 5-7 days |
Lay telecom and electrical ducts together instead of separately. |
Saves 5-6 days |
|
Begin road widening on completed sections while utilities are being laid in other areas. |
Saves 7-10 days |
|
Start footpath and drainage work while sub-base preparation is ongoing. |
Saves 5-6 days |
|
2. Use of Advanced Construction Methods |
Use precast concrete ducts for utilities instead of traditional RCC work. |
Saves 7-10 days |
Deploy Ready-Mix Concrete (RMC) for road surfacing to speed up paving. |
Saves 4-6 days |
|
Use mechanized excavation and backfilling instead of manual work. |
Saves 7-10 days |
|
3. Improved Resource Allocation |
Increase night shifts for critical work like asphalt laying and surfacing. |
Saves 7-10 days |
Deploy multiple work teams for different sections simultaneously. |
Saves 5-7 days |
|
4. Efficient Material & Logistics Planning |
Procure all key materials in advance to avoid site delays. |
Saves 5-7 days |
Arrange backup machinery and workforce to avoid idle time. |
Saves 3-5 |
Category |
Role |
Key Responsibilities |
Approx. No. Required |
Planning & Supervision |
Project Manager |
Overall coordination, approvals, timeline management |
1 |
Road Design Engineer |
Designing road alignment, widening plan, and cross-sections |
1 |
|
Structural Engineer |
Ensuring stability of underground utilities, footpaths, and road |
1 |
|
Surveyor |
Conducting site surveys, marking, and leveling |
2 |
|
Site Engineers |
On-site supervision, quality control, coordination with contractors |
2-3 |
|
Safety Officer |
Ensuring worker safety, enforcing safety protocols |
1 |
|
Excavation & Earthworks |
Excavator Operators |
Digging trenches for utility ducts and road widening |
4-5 |
Dump Truck Drivers |
Transporting excavated soil and materials |
3-4 |
|
Utility Installation |
Electricians |
Laying and connecting electrical cables and streetlights |
5-6 |
Plumbers |
Installing water pipelines and drainage systems |
3-4 |
|
OFC Technicians |
Laying fiber optic cables and telecom ducts |
3-4 |
|
Civil & Structural Works |
Masons |
Concrete work for footpaths, drains, and ducts |
8-10 |
Road Workers |
Asphalt laying, compacting, leveling |
10-12 |
|
Concrete Finishers |
Finishing curbs, footpaths, drainage structures |
4-5 |
|
Machinery Operators |
Road Roller Operators |
Compacting asphalt and sub-base layers |
2 |
Paver Machine Operators |
Operating bitumen/asphalt laying machines |
2 |
|
Smart Infrastructure |
IT Technicians |
Installing smart poles, traffic sensors, and CCTVs |
3-4 |
Miscellaneous Workers |
Welders |
Fabrication and installation of railings, signboards |
2-3 |
Painters |
Road marking, signage painting |
3-4 |
|
Helpers & General Laborers |
Assisting in all tasks, material handling, miscellaneous work |
30-40 |
Category | Key Aspects |
---|---|
1. Roadside Safety Features | Crash barriers, bollards, pedestrian railings for accident prevention |
2. Road Markings & Signages | Thermoplastic markings, reflective signboards, wayfinding signage |
3. Utility Coordination & Planning | Common utility ducts, coordination with utility agencies |
4. Smart Road Infrastructure | Smart poles, EV charging stations, underground waste bins |
5. Water Management & Flood Prevention | Permeable pavements, stormwater drains, rainwater harvesting |
6. Landscaping & Aesthetic Enhancements | Green verges, vertical gardens, tree guards |
7. Road Longevity & Maintenance | Pavement monitoring, pothole repair strategy, material choice |
8. Smart Road Safety Measures | AI-based traffic sensors, rumble strips, CCTV surveillance |
9. Construction Quality & Environmental Compliance | Dust suppression, noise barriers, use of recycled materials |
10. Emergency & Disaster Preparedness | Emergency parking bays, flood-resistant design, fire hydrants |
No comments:
Post a Comment