Friday, March 14, 2025

All about Smart Roads Constructions

A. Step by step guide for road construction 


Step No.

Activity

Details

1

Project Planning & Feasibility Study

Identify the road stretch, assess existing conditions, conduct traffic analysis, and perform soil investigation & topographical surveys.

2

Preparation of Detailed Project Report (DPR)

Includes road width, pavement type, utility plans, drainage, lighting, smart elements, and cost estimates.

3

Preparation of Detailed Drawings & Approvals

Obtain necessary approvals for road cross-sections, utility duct layouts, drainage plans, lighting, and landscape designs.

4

Shifting of Existing Utilities

Relocate underground water pipelines, electricity cables, telecom ducts, and sewage lines to prevent conflicts.

5

Site Clearance & Marking

Remove encroachments, debris, and existing damaged pavement. Mark road alignment and positions for smart elements.

6

Excavation & Preparation of Subgrade

Excavate to required depth and compact the subgrade. Lay geo-textile fabric (if needed) for soil stabilization.

7

Stormwater Drainage Construction

Construct side drains, culverts, and underground stormwater drainage channels to prevent waterlogging.

8

Laying of Utility Ducts

Install underground ducts for electricity, telecom, gas, fiber optic cables, and water supply with maintenance access points.

9

Base Layer Construction

Lay Granular Sub-Base (GSB) followed by Wet Mix Macadam (WMM) for road stability, ensuring proper compaction.

10

Pavement Construction

Based on road type: bituminous or concrete 

11

Footpath & Pedestrian Infrastructure

Construct footpaths using interlocking tiles/concrete, install tactile paving for visually impaired, and develop pedestrian-friendly walkways.

12

Smart Elements Installation

Install smart poles, LED streetlights, CCTV cameras, traffic signals, smart parking sensors, EV charging stations, and integrate Wi-Fi & IoT-based monitoring.

13

Horticulture & Green Cover Development

Develop green belts, plant native trees, install tree guards, vertical gardens, and landscape the medians and footpaths.

14

Signage & Road Markings

Install traffic signboards, zebra crossings, lane markings, reflective studs, and digital traffic information systems for safety.

15

Final Inspection & Quality Check

Conduct a thorough quality audit, check pavement smoothness, utility ducts, smart installations, and ensure stormwater drainage efficiency.

16

Commissioning & Handover

Open the road for public use, conduct final inspections, rectify defects, integrate smart monitoring systems, and complete project documentation.



B. Drawings Required for Smart Road Construction


Drawing Name

Purpose

Details Included

Topographic Survey & Existing Utility Plan

To assess existing land conditions and identify existing utilities.

Road width, contours, slopes, existing utilities (water, electricity, telecom, sewer), trees, encroachments.

Alignment & Cross-Section Drawing

Defines road alignment and width, ensuring compliance with road design standards.

Road width, lanes, shoulders, footpath, cycle tracks, median, ROW (Right of Way).

Soil Investigation & Subgrade Preparation Plan

Helps in designing the base and sub-base layers of the road.

Soil type, bearing capacity, excavation depth, compaction details, stabilization layers (if required).

Stormwater Drainage Plan

Ensures proper water drainage to prevent flooding and waterlogging.

Location of stormwater drains, slopes, manholes, outfalls, rainwater harvesting pits.

Utility Duct Layout Plan

Ensures organized placement of underground utilities without conflicts.

Positions of ducts for electricity, water, sewage, telecom, fiber optics, and gas pipelines.

Pavement Layer Composition & Structural Design

Determines the road strength and durability.

Road base, sub-base, bituminous/concrete layer details, thickness, and material specifications.

Road Profile & Longitudinal Section

Shows elevation variations along the road length.

Gradient, elevation, slope details, and cut-and-fill requirements.

Bituminous/Concrete Pavement Design Details

Ensures proper material and layer design for road longevity.

Type of pavement, thickness of each layer, material composition, reinforcement details (for concrete roads).

Footpath & Pedestrian Infrastructure Plan

Ensures safe and accessible pedestrian movement.

Width of footpaths, material details, tactile paving for visually impaired, ramps, street furniture locations.

Smart Infrastructure & Electrical Plan

Placement of smart elements and electrical systems.

Streetlights, smart poles, CCTV locations, Wi-Fi hotspots, traffic signals, EV charging stations.

Horticulture & Landscaping Plan

Defines green spaces for aesthetics and environmental benefits.

Locations of trees, shrubs, planters, green medians, vertical gardens, and irrigation system.

Signage & Road Marking Plan

Enhances road safety and visibility for users.

Traffic signs, zebra crossings, lane markings, speed limits, direction boards, reflective studs.

Junction & Traffic Management Plan

Improves traffic flow and safety at intersections.

Roundabouts, signals, pedestrian crossings, traffic islands, lane bifurcations.

Final As-Built Drawings

Document actual execution and any modifications made.

Final layouts, changes made during construction, approved modifications, and location of all underground utilities.

GFC (Good for Construction) Drawings are final approved drawings that contractors and engineers use for actual execution of the project. These drawings include detailed dimensions, materials, specifications, and construction techniques to be followed on-site. They are issued after all necessary approvals, ensuring that the design is practically feasible and executable. A detailed GFC drawing is made after topographic survey with detailing all elements. For executable, element wise GFC are made . 

C. Test needed in road construction work. 

Stage

Essential Test

Purpose

Conducted By

1. Soil/Subgrade Preparation

CBR Test (California Bearing Ratio)

Checks soil strength for load-bearing capacity.

Geotechnical Engineer / Third-Party Lab


Soil Compaction Test (Field Dry Density Test)

Ensures proper soil compaction for stability.

Contractor QC Team / Site Engineer

2. Base & Sub-Base (GSB, WMM, etc.)

Aggregate Impact Value Test

Ensures aggregates are strong and durable.

Site Engineer / Third-Party Lab


Gradation Test

Confirms correct particle size distribution for base layers.

Contractor QC Team

3. Bituminous Road Work

Bitumen Content Test

Ensures correct bitumen percentage in the mix.

Third-Party Lab / Asphalt Plant


Marshall Stability Test

Checks strength and stability of bituminous mix.

Government / Private Testing Lab


Core Cutting Test

Confirms the thickness of the laid bituminous layer.

Third-Party Lab

4. Concrete Road (If applicable)

Slump Test

Checks workability of concrete before laying.

Site Engineer / Contractor


Cube Strength Test

Ensures concrete attains required strength.

Third-Party Testing Lab

5. Final Road Quality Check

Benkelman Beam Deflection Test

Measures the structural strength of the pavement.

Government / Third-Party Testing Agency


Pavement Roughness Test (IRI – International Roughness Index)

Ensures smooth driving surface.

Specialized Survey Agency


C.1 Testing requirement for other smart road components 

Component

Test Name

Purpose

Stage of Testing

Drain Construction

Concrete Strength Test (Cube Test)

Ensures required strength of RCC drains.

After 7, 14, and 28 days of casting

Water Permeability Test

Checks for water leakage or seepage.

After curing of concrete

Gradient & Flow Test

Ensures proper drainage slope and water flow.

After construction, before road laying

Utility Ducts

Compaction Test for Backfilling

Ensures soil compaction around ducts.

After backfilling of trenches

Air Pressure Test (for conduits)

Checks for air-tightness of electrical and telecom conduits.

Before cable installation

Water Flow Test (for water lines)

Ensures proper water supply and pressure in pipes.

After pipe installation, before covering

Street Lights

Earth Resistance Test

Ensures proper earthing for safety.

Before energizing the system

Illumination Level Test (Lux Test)

Checks if lighting meets required brightness levels.

After installation, during night testing

Pole Load Test

Ensures pole can withstand wind and load conditions.

Before pole erection

Footpath & Pavement

Compressive Strength Test (for paver blocks)

Ensures durability of footpath paver blocks.

Before installation

Skid Resistance Test

Ensures anti-slip properties of footpath surface.

After completion

Signages & Road Markings

Retro-Reflectivity Test

Ensures visibility of road signs and markings at night.

After application

Stormwater Management

Percolation Test (for rainwater harvesting pits)

Checks ground absorption capacity.

Before constructing pits


C.2 PDI and its need 

PDI (Pre-Dispatch Inspection) is a quality check conducted before materials or equipment are dispatched from the manufacturer or supplier to the project site. It ensures that items meet the required specifications, standards, and quality criteria before they are delivered.

Item

Why is PDI Required?

When to Conduct PDI?

Who Conducts It?

Street Light Poles & Fixtures

Ensures proper fabrication, height, alignment, and wiring.

Before dispatch from manufacturer.

Vendor + Project QC Team

LED Street Lights

Checks wattage, lumens, material quality, and IP rating.

Before dispatch.

Vendor + Electrical Engineer

Utility Duct Pipes (HDPE/PVC/GI)

Ensures correct diameter, material thickness, and strength.

Before dispatch.

Vendor + Site Engineer

Precast RCC Drain Covers

Verifies dimensions, strength, and load-bearing capacity.

Before dispatch.

Vendor + Structural Engineer

Paver Blocks for Footpath

Checks compressive strength, uniformity, and anti-skid properties.

Before dispatch.

Vendor + Quality Inspector

Signboards & Road Markings Paint

Ensures retro-reflectivity, durability, and compliance with IRC standards.

Before dispatch.

Vendor + Traffic Engineer

Smart Road Furniture (Benches, Bollards, Railings)

Ensures correct material, finish, and durability.

Before dispatch.




D. Layers in a Road 

Layer

Purpose

Material Used

Applicable to

1. Subgrade

Acts as the foundation of the road, bearing the load of traffic.

Compacted natural soil, sand, geotextiles (if needed for stabilization).

All roads (bituminous & concrete)

2. Granular Sub-Base (GSB)

Provides drainage and distributes load evenly.

Crushed stone, gravel, sand, fly ash (in some cases).

All roads

3. Base Course (WMM/WBM)

Provides structural strength to the road.

- WMM (Wet Mix Macadam): Crushed aggregates, stone dust, water. - WBM (Water Bound Macadam): Aggregates bound with water and compacted.

All roads

4. Binder Course (For Bituminous Roads)

Intermediate layer to bind base and surface course.

- Bituminous Macadam (BM): Coarse aggregates mixed with bitumen. - Dense Bituminous Macadam (DBM): Stronger bituminous mix.

Bituminous roads only

5. Surface Course (Wearing Layer)

Provides a smooth, durable surface for vehicles.

- Bituminous Roads: Bituminous Concrete (BC), Mastic Asphalt. - Concrete Roads: Pavement Quality Concrete (PQC) with reinforcement.







E. Construction steps for utility ducts, drain, road and electric street poles 

E.1 Utility ducts 

Step

Activity

Description

Tentative Time

1. Marking & Excavation

Mark trench alignment & dig as per depth

Done as per design considering future utilities.

3-5 days

2. Base Preparation

Leveling and compacting base

Ensures stability and prevents settlement.

1-2 days

3. Duct Installation

Laying RCC/PVC pipes or pre-cast ducts

Placing conduits for electrical, telecom, water, etc.

5-7 days

4. Manhole & Chamber Construction

Creating access points at intervals

Manholes allow maintenance & future expansion.

4-5 days

5. Covering & Backfilling

Concrete encasement & refilling trench

Protects ducts and restores surface.

3-4 days

6. Surface Restoration

Rebuilding footpath or road surface

Final finishing depending on surface type.

4-6 days


E.2 Drain 

Step

Activity

Description

Tentative Time

1. Marking & Excavation

Layout alignment & digging

As per design & required depth.

3-5 days

2. Base Preparation

Leveling & compacting base

Ensures proper gradient for water flow.

2-3 days

3. Formwork & Reinforcement

Placing steel reinforcement (if RCC drain)

Required for concrete drains to enhance durability.

4-6 days

4. Drain Casting (RCC/Masonry)

Concrete pouring or brick masonry

Constructing the drain walls & base.

5-7 days

5. Curing & Strength Gain

Allow concrete to gain strength

Essential for durability & crack prevention.

7-10 days

6. Cover Slab/Grating Fixing

Placing RCC or iron grates

Protects drain & allows easy cleaning.

3-4 days

7. Surface Restoration

Rebuilding footpath/road if required

Final finishing work.

3-5 days


E.3 Roads 

Step

Activity

Description

Tentative Time

1. Site Preparation & Excavation

Clearing, marking, and excavation

Removal of obstructions, grading, and preparation of the site.

5-7 days

2. Subgrade Preparation

Compaction of natural soil

Stabilizing the soil base to prevent settlement.

3-5 days

3. Sub-Base Layer (GSB - Granular Sub-Base)

Laying crushed aggregates and compacting

Ensures load distribution and drainage.

4-6 days

4. Base Layer (WMM/WBM)

Laying Wet Mix Macadam (WMM) or Water Bound Macadam (WBM)

Provides structural strength.

5-7 days

5. Binder Course (For Bituminous Roads)

Applying Bituminous Macadam (BM) or Dense Bituminous Macadam (DBM)

Acts as an intermediate layer to bind the base and surface.

4-6 days

6. Surface Course (Wearing Layer)

Laying Bituminous Concrete (BC) or Pavement Quality Concrete (PQC)

Final smooth surface for vehicles.

4-6 days

7. Curing (For Concrete Roads Only)

Allowing concrete to gain strength

Essential for durability and preventing cracks.

7-14 days (if PQC)

8. Road Marking & Signage Installation

Painting lane markings, placing road signs

Enhances safety and traffic management.

2-4 days

9. Final Inspection & Opening to Traffic

Checking quality and final approvals

Ensuring proper construction before opening.

1-2 days


E.4 Street Light 

Step

Activity

Description

Tentative Time

1. Site Survey & Design Planning

Identifying pole locations and preparing the layout

Ensures optimal light coverage and alignment with road design.

2-3 days

2. Excavation for Pole Foundation

Digging pits for pole installation

Depth depends on pole height and wind load.

2-4 days

3. Foundation Construction

Laying concrete foundation for stability

Ensures pole strength and durability.

4-6 days

4. Pole Erection & Alignment

Installing poles and aligning them properly

Ensures uniform height and positioning.

3-5 days

5. Cable Laying & Ducting

Placing underground cables for power supply

Done through pre-installed ducts or new trenches.

5-7 days

6. Fixing Electrical Components

Installing junction boxes, control panels, and switches

Ensures power regulation and control.

3-5 days

7. Light Fixture Installation

Fixing LED lights, brackets, and fittings

Mounting the lighting system on poles.

2-4 days

8. Connection & Testing

Connecting to the power supply and checking functionality

Ensures proper illumination and safety compliance.

3-5 days

9. Final Inspection & Commissioning

Checking alignment, brightness, and system efficiency

Ensures smooth operation before handover.

2-3 days


F. PERT chart preparation ( assume 2 km smart road ) 

Task Name

Duration (Days)

Dependency (Must be Completed Before Starting)

Survey & Design

15

None

Utility Shifting Planning

10

Survey & Design

Excavation for Ducts (Electric, Water, Telecom)

20

Utility Shifting Planning

Laying Electrical & Water Pipelines

25

Excavation for Ducts

Telecom & OFC Laying

15

Excavation for Ducts

Backfilling & Surface Restoration

20

Laying Electrical & Water Pipelines, Telecom & OFC Laying

Road Widening & Sub-base Preparation

25

Backfilling & Surface Restoration

Drainage & Footpath Construction

20

Road Widening & Sub-base Preparation

Asphalt/Paver Road Surfacing

15

Drainage & Footpath Construction

Smart Features Installation (Lights, Signage)

10

Asphalt/Paver Road Surfacing

Final Road Markings & Testing

7

Smart Features Installation

Project Handover

5

Final Road Markings & Testing


F.1 How do I speed up the work 

Category

Optimized Strategy

Expected Time Savings

1. Parallel Execution of Tasks

Start utility shifting and excavation simultaneously instead of sequentially.

Saves 5-7 days

Lay telecom and electrical ducts together instead of separately.

Saves 5-6 days

Begin road widening on completed sections while utilities are being laid in other areas.

Saves 7-10 days

Start footpath and drainage work while sub-base preparation is ongoing.

Saves 5-6 days

2. Use of Advanced Construction Methods

Use precast concrete ducts for utilities instead of traditional RCC work.

Saves 7-10 days

Deploy Ready-Mix Concrete (RMC) for road surfacing to speed up paving.

Saves 4-6 days

Use mechanized excavation and backfilling instead of manual work.

Saves 7-10 days

3. Improved Resource Allocation

Increase night shifts for critical work like asphalt laying and surfacing.

Saves 7-10 days

Deploy multiple work teams for different sections simultaneously.

Saves 5-7 days

4. Efficient Material & Logistics Planning

Procure all key materials in advance to avoid site delays.

Saves 5-7 days

Arrange backup machinery and workforce to avoid idle time.

Saves 3-5


G. Manpower requirement in the project ( assuming above one )

Category

Role

Key Responsibilities

Approx. No. Required

Planning & Supervision

Project Manager

Overall coordination, approvals, timeline management

1

Road Design Engineer

Designing road alignment, widening plan, and cross-sections

1

Structural Engineer

Ensuring stability of underground utilities, footpaths, and road

1

Surveyor

Conducting site surveys, marking, and leveling

2

Site Engineers

On-site supervision, quality control, coordination with contractors

2-3

Safety Officer

Ensuring worker safety, enforcing safety protocols

1

Excavation & Earthworks

Excavator Operators

Digging trenches for utility ducts and road widening

4-5

Dump Truck Drivers

Transporting excavated soil and materials

3-4

Utility Installation

Electricians

Laying and connecting electrical cables and streetlights

5-6

Plumbers

Installing water pipelines and drainage systems

3-4

OFC Technicians

Laying fiber optic cables and telecom ducts

3-4

Civil & Structural Works

Masons

Concrete work for footpaths, drains, and ducts

8-10

Road Workers

Asphalt laying, compacting, leveling

10-12

Concrete Finishers

Finishing curbs, footpaths, drainage structures

4-5

Machinery Operators

Road Roller Operators

Compacting asphalt and sub-base layers

2

Paver Machine Operators

Operating bitumen/asphalt laying machines

2

Smart Infrastructure

IT Technicians

Installing smart poles, traffic sensors, and CCTVs

3-4

Miscellaneous Workers

Welders

Fabrication and installation of railings, signboards

2-3

Painters

Road marking, signage painting

3-4

Helpers & General Laborers

Assisting in all tasks, material handling, miscellaneous work

30-40


*Urban mobility planner ( for planning )


H. Important Aspects in Road Construction Beyond Basic Layers
CategoryKey Aspects
1. Roadside Safety FeaturesCrash barriers, bollards, pedestrian railings for accident prevention
2. Road Markings & SignagesThermoplastic markings, reflective signboards, wayfinding signage
3. Utility Coordination & PlanningCommon utility ducts, coordination with utility agencies
4. Smart Road InfrastructureSmart poles, EV charging stations, underground waste bins
5. Water Management & Flood PreventionPermeable pavements, stormwater drains, rainwater harvesting
6. Landscaping & Aesthetic EnhancementsGreen verges, vertical gardens, tree guards
7. Road Longevity & MaintenancePavement monitoring, pothole repair strategy, material choice
8. Smart Road Safety MeasuresAI-based traffic sensors, rumble strips, CCTV surveillance
9. Construction Quality & Environmental ComplianceDust suppression, noise barriers, use of recycled materials
10. Emergency & Disaster PreparednessEmergency parking bays, flood-resistant design, fire hydrants

No comments:

Post a Comment