Saturday, March 15, 2025

All About Building Construction

 A. Step by Step guide for construction 


Stage

Key Steps

Description of Tasks

Timeline Estimate

1. Project Concept & Feasibility

Feasibility Study

Assess site, demand, budget, and legal requirements

1-2 months

Budget Estimation

Initial cost estimation, financing, approvals


Site Selection

Land procurement, accessibility, zoning compliance


2. Design & Planning

Appointment of Architects & Consultants

Hire architect, structural engineer, MEP consultant, landscape consultant

2-4 months

Conceptual Design

Prepare preliminary layout, floor plans, 3D visualizations


Detailed Design & Drawings

Structural, architectural, electrical, plumbing, HVAC, fire safety, landscape, façade


Environmental & Government Approvals

Fire NOC, environmental clearance, local authority approvals


3. Tendering & Contractor Selection

Preparation of Tender Documents

BOQ, technical specifications, RFP preparation

1-2 months

Tender Floating & Evaluation

Invite bids, evaluate technical & financial proposals


Contract Signing

Award contract, finalize payment schedule, mobilization advance


4. Site Preparation & Initial Works

Site Clearance & Levelling

Remove debris, tree cutting, grading

1 month

Soil Testing & Survey

Geotechnical tests, topographic survey


Temporary Site Setup

Site office, storage, labor camps, safety measures


5. Foundation & Substructure

Excavation & Earthwork

Digging for foundation and basement (if applicable)

2-3 months

Foundation Construction

Piling, footing, plinth beam


Waterproofing & Basement Work

Underground tank, sump pits, drainage


6. Superstructure (Frame & Walls)

RCC/Steel Frame Erection

Column, beam, slab casting (floor-wise)

4-6 months

Masonry & Partition Walls

Brick/block work for walls, plastering


7. Mechanical, Electrical & Plumbing (MEP) Works

Electrical & HVAC Installation

Wiring, ducting, transformers, panels

4-6 months (parallel)

Plumbing & Firefighting

Water supply, drainage, fire suppression systems


IT & Networking

CCTV, access control, data cabling


8. Exterior & Interior Finishing

Flooring & Tiling

Marble, tiles, wood flooring

3-5 months

False Ceiling & Paint

Interior & exterior finishes


Façade & Window Installation

Glass, aluminum cladding, doors & windows


9. External Development & Landscaping

Paving & Parking

Driveways, parking areas, signage

1-2 months

Green Spaces & Street Furniture

Lawns, gardens, fountains, seating areas


10. Testing, Inspection & Handover

Quality Testing

Structural integrity, water & electrical tests

1-2 months

Authority Approvals

Fire safety, occupancy certificate, municipal clearance


Final Handover

System commissioning, training, facility management setup




B. Different types of drawings prepared for the building 

Stage

Drawing Type (Technical Name)

Purpose & Description

Concept & Planning

Conceptual Drawings

Rough sketches to visualize design ideas and spatial planning

Site Plan

Shows the building’s location, roads, landscape, and site boundaries

Zoning & Compliance Drawings

Ensures adherence to building laws, setbacks, and height restrictions

Design Development

Floor Plan

A top-down view showing the layout of rooms, walls, and circulation spaces

Elevation Drawings

Front, side, and rear views showing the external appearance

Section Drawings

Vertical cut-through of the building showing internal details

3D Perspective Views

Rendered images to visualize the final design realistically

Approval & Tendering

Approval Drawings

Submitted to authorities for obtaining building permissions

Fire & Safety Drawings

Includes fire exits, sprinkler systems, and safety features

Tender Drawings

Used for bidding and contractor selection, includes material specifications

Execution & Construction

Good for Construction (GFC) Drawings

Finalized, detailed drawings used on-site for execution

Shop Drawings

Highly detailed drawings for fabrication (e.g., doors, windows, joinery)

As-Built Drawings

Records the exact work executed, including any on-site modifications


B.1 Element wise drawings differentiation 

Drawing Type

Technical Name

Key Features & Differences

Building Layout

Floor Plan

Top view showing rooms, walls, doors, and windows

Exterior Appearance

Elevation Drawing

Flat 2D view showing building’s façade from different angles

Internal Sections

Section Drawing

Vertical cut-through to show internal structure, ceiling height, and materials

Detailed Construction

Working Drawing

Highly detailed technical drawing for builders and engineers

Electrical Layout

Electrical Plan

Placement of switches, lights, and power outlets

Plumbing System

Plumbing & Drainage Plan

Shows water supply, drainage pipes, and fittings

Fire Safety

Fire Evacuation Plan

Emergency exits, hydrants, sprinklers, and alarms

HVAC Layout

Mechanical Drawings

Ductwork, ventilation, and air conditioning layout


B.2 What is GFC how is it different from conceptual drawings 

conceptual drawing is the starting point of the design, and through multiple refinements, it transforms into a Good for Construction (GFC) drawingConceptual Drawings are for early-stage planning and approvals.GFC Drawings are final construction-ready documents, ensuring accurate execution on-site.

For example conceptual drawing of the floor plan are Created in the early design stage to present basic layouts and spatial arrangements.Focuses on zoning, room sizes, circulation, and broad functional areas.No construction-level details like material specifications, wall thickness, structural components, or MEP (Mechanical, Electrical, Plumbing) integration. However GFC will have precise measurements, wall thicknesses, door/window placements, slab cutouts, column positions, flooring details, service shafts, and MEP coordination. These are ready to work drawings for site engineer's. 

Category

GFC Drawing Type

Purpose

Architectural

Floor Plans

Shows room layout, doors, windows, and circulation

Elevations

External view of the building from all sides

Sections

Vertical cuts showing internal details like ceiling heights, walls, and materials

Staircase Details

Design, riser/tread dimensions, and railing details

Structural

Foundation Plan

Shows footings, columns, and reinforcement details

Column Layout

Positions and sizes of structural columns

Slab & Beam Layout

Placement of beams, slabs, and reinforcement details

MEP (Mechanical, Electrical, Plumbing)

Electrical Layout

Wiring, lighting, switchboards, and power sockets

Plumbing Layout

Water supply, drainage, and pipe routes

HVAC Plan

Ducting, ventilation, and air conditioning systems

Fire & Safety

Fire Evacuation Plan

Fire exits, sprinklers, smoke detectors

Firefighting System

Hydrants, extinguishers, and alarm systems

Landscaping & Site Work

Site Plan

Roads, parking, green spaces, and pathways

Boundary Wall Details

Dimensions and materials of the compound wall


In large buildings we divide the floor into sections and prepare drawings seperately for understanding. GFC drawings of different things are prepared by different specialist in close coordination. Structure engineer will tell how . Also some sections or features require detailed information like staircases, some wall , front facade, glass work etc. these can be seen in shop drawings. 

C. Testing need in a building construction work 

Stage

Element

Test Name

Purpose (Why is it needed?)

Who Conducts It?

Material for PDI & What is Checked?

1. Pre-Construction

Soil

Soil Bearing Capacity (SBC) Test

Checks if soil can bear the building load.

Geotechnical Engineer

-


Soil Compaction Test

Ensures soil is compacted to prevent settlement.

Site Engineer

-

Water

pH & Chemical Test

Ensures water quality for concrete mixing.

Testing Lab

-

2. Foundation & Structural Work

Concrete

Slump Test

Checks concrete workability before pouring.

Site Engineer

-


Cube Compression Test

Ensures concrete strength after curing.

Testing Lab

-

Steel

Tensile Strength Test

Ensures steel reinforcement can bear load.

Manufacturer/Testing Lab

Steel Bars – Diameter, strength, bendability, rust-free surface

Bricks

Compressive Strength Test

Ensures bricks can handle load without cracking.

Site Engineer

Bricks – Size, shape, strength, water absorption

3. Superstructure Work

Plaster

Adhesion Test

Ensures plaster sticks well to walls.

Site Engineer

-

Flooring/Tiles

Water Absorption Test

Prevents tile breakage due to water absorption.

Manufacturer/Site Engineer

Tiles & Stone Slabs – Dimensions, cracks, polish, water absorption

4. MEP (Mechanical, Electrical, Plumbing) Work

Plumbing

Pressure Test

Checks pipes for leaks under pressure.

Plumber/Site Engineer

Pipes & Fittings – Thickness, material quality, leak-proof joints

Electrical

Insulation Resistance Test

Ensures electrical wiring is safe.

Electrical Engineer

Cables & Switches – Wire gauge, insulation, conductor quality

HVAC

Air Leakage Test

Prevents energy loss in ducting.

HVAC Contractor

Ducting Material – Thickness, leakage, insulation quality

5. Finishing Stage

Paint

Adhesion & Thickness Test

Ensures paint is applied properly and evenly.

Paint Contractor

-

Glass

Impact & Toughness Test

Checks if glass can handle impacts safely.

Manufacturer

Glass Panels – Strength, thickness, edge polishing

Waterproofing

Ponding Test

Checks waterproofing before final finishes.

Waterproofing Contractor

-

6. Post-Construction & Final Testing

Building

Structural Load Test

Ensures building can handle expected loads.

Structural Engineer

-

Fire Safety

Fire Hydrant Flow Test

Ensures fire hydrants provide enough pressure.

Fire Safety Officer

Fire Safety Equipment – Pressure, flow rate, functionality

Elevators

Lift Load Test

Checks if lifts can handle the rated load.

Elevator Contractor

Elevators & Lift Components – Load-bearing capacity, safety mec



D. Make a PERT chart for a building construction work. Assume it to be a two floor building 

Task ID

Activity

Predecessor(s)

Duration

A

Site Preparation & Earthwork

None

10

B

Foundation Work (Excavation, PCC, Footing, Plinth Beam)

A

20

C

Ground Floor Columns & Beams

B

15

D

Ground Floor Slab Casting (Shuttering, Reinforcement, Concrete)

C

10

E

First Floor Columns & Beams

D

15

F

First Floor Slab Casting (Shuttering, Reinforcement, Concrete)

E

10

G

Ground Floor Brickwork & Partition Walls

D

25

H

First Floor Brickwork & Partition Walls

F

25

I

Plastering & Waterproofing

G, H

15

J

Electrical & Plumbing (Conduits & Pipes)

G, H

20

K

Flooring & Tiling

I, J

20

L

Painting & Finishing

K

15

M

External Works (Landscaping, Parking, Boundary Wall)

L

10

N

Final Testing & Handover

M

10


D.1 How can I expedite the work 

To reduce the project duration from 175 days to ~125 days, consider the following time-saving strategies:

1. Parallel Execution of Tasks

  • Start First Floor Columns before Ground Floor Brickwork is fully completed.
  • Begin Plastering on the Ground Floor while First Floor Brickwork is ongoing.
  • Execute Electrical and Plumbing work alongside Plastering instead of waiting for it to finish.

2. Use Precast Components

  • Use precast slabs, lintels, and stairs instead of casting them on-site.
  • This eliminates curing time delays and speeds up construction by 10-12 days.

3. Use High-Performance Concrete (HPC) & Ready-Mix Concrete (RMC)

  • HPC has faster curing times, allowing slab and column work to move ahead 5-7 days faster.
  • RMC avoids on-site mixing delays, reducing 5-6 days.

4. Efficient Shuttering Techniques

  • Use Mivan or aluminum formwork for slab casting, which speeds up formwork removal.
  • Saves 7-10 days in overall structure work.

5. Deploy Multiple Work Crews

  • Parallel teams for flooring, painting, and finishing can save 10-12 days.
  • Specialized teams for electrical and plumbing work allow work to move simultaneously with plastering.

6. Efficient Procurement & Logistics Planning

  • Ensure no material shortages that could cause work stoppages.
  • Saves 5-7 days by preventing delays in procurement.
D2. Graphical Understanding 






E. Manpower Requirement in the project 

category

Role

Purpose / Responsibilities

Estimated Manpower

Management & Planning

Project Manager

Oversees the entire project, manages resources, timeline, and coordination.

1-2

Site Engineer

Supervises on-site work, quality control, and compliance with design.

2-3

Architect

Designs the building layout, aesthetics, and usability.

1

Structural Engineer

Ensures stability, load-bearing capacity, and structural integrity.

1

Quantity Surveyor

Estimates material requirements, cost control, and billing.

1

Safety Officer

Ensures compliance with safety norms and reduces site hazards.

1

Procurement Manager

Manages purchase and supply of construction materials.

1

Civil & Structural Works

Masons

Constructs brickwork, plastering, and finishing works.

30-40

Carpenters

Builds formwork for concrete slabs, beams, and columns.

15-20

Steel Fixers (Bar Benders)

Cuts, bends, and fixes steel reinforcement for RCC work.

10-15

Concrete Workers

Mixes, pours, and levels concrete.

15-20

Scaffolding Workers

Installs and maintains scaffolding for safe work at height.

5-10

General Laborers (Helpers)

Assists in carrying materials, mixing cement, and general site activities.

40-50

Mechanical, Electrical & Plumbing (MEP)

Electricians

Installs wiring, lighting, and electrical systems.

10-15

Plumbers

Installs water supply, drainage, and sanitation systems.

10-12

HVAC Technicians

Installs heating, ventilation, and air conditioning (if applicable).

5-7

Lift Technicians

Installs and maintains elevators (if applicable).

2-3

Finishing & Interiors

Painters

Applies paint, polishes, and surface finishes.

10-15

Tile & Marble Layers

Installs flooring, wall tiles, and marble surfaces.

10-15

False Ceiling Workers

Installs false ceilings and gypsum board partitions.

5-10

Glass & Aluminium Workers

Installs windows, doors, and glass facades.

5-10

Interior Decorators

Designs and installs interior furnishings and lighting.

3-5

External & Landscaping

Pavers & Road Workers

Lays external pavements, driveways, and pathways.

5-10

Gardeners (Landscapers)

Plants trees, maintains green areas, and landscaping.

3-5

Gate & Boundary Workers

Constructs fences, gates, and boundary walls.

5-7

Security & Support

Security Guards

Ensures site safety and material security.

5-7

Cleaning Staff

Keeps the site clean and removes construction debris.

3-5

Total Manpower Requirement

-

At peak stage: 150-200 workers

150-200


F. All about Building components 

Component

Description

Function

Sub-Parts

Types

Foundation

The lowest part of the building structure, set in the ground.

Provides stability, distributes the load to the soil, and prevents settling.

Footings, Piles, Grade Beams

Shallow (e.g., Spread Footing), Deep (e.g., Pile Foundation)

Plinth

The portion between the foundation and the ground floor.

Prevents moisture from entering the building and raises the structure above ground level.

Plinth Beam, Damp Proof Course (DPC)

Low Plinth, High Plinth

Columns

Vertical structural elements supporting the building.

Transfers the load from the slab and beams to the foundation.

Reinforcement, Formwork, Concrete Cover

RCC Columns, Steel Columns, Composite Columns

Beams

Horizontal load-bearing elements.

Transfers load from slabs to columns, preventing excessive bending.

Reinforcement, Stirrups, Concrete Cover

Simply Supported, Cantilever, Continuous

Slab

Flat structural component forming the floors and ceilings.

Supports the load of occupants and furniture, providing separation between floors.

Reinforcement, Concrete, Shuttering

One-Way Slab, Two-Way Slab, Flat Slab

Walls

Vertical enclosures that provide security and support.

Separates spaces, bears loads (in some cases), and provides insulation.

Brickwork, Reinforcement (for RCC Walls), Plaster

Load-Bearing Walls, Partition Walls, Shear Walls

Roof

Top covering of a building structure.

Protects from weather conditions and provides insulation.

Trusses, Rafters, Purlins, Roofing Sheets

Flat Roof, Pitched Roof, Shell Roof

Doors

Openings that allow entry and exit from rooms and buildings.

Provides access and security.

Frame, Shutters, Hinges, Locks

Wooden, Metal, Glass, uPVC

Windows

Openings in walls allowing ventilation and light.

Provides air circulation, light, and visibility.

Frame, Glass, Shutters

Casement, Sliding, Fixed, Louvered

Staircase

Vertical circulation system consisting of steps.

Provides access between different floors.

Steps, Landings, Handrails, Balusters

Straight, Spiral, Dog-Legged, Open-Well

Flooring

The surface of a room on which people walk.

Provides a durable and aesthetic walking surface.

Subfloor, Finishing Layer, Skirting

Tile, Marble, Wooden, Concrete

Ceiling

Overhead surface inside a building.

Conceals structural elements and enhances aesthetics.

False Ceiling, Decorative Elements

Plasterboard, POP, Wooden, Metal

Electrical System

Network of wiring and fixtures supplying power.

Provides electricity for lighting, appliances, and safety.

Wiring, Switches, MCBs, Distribution Boards

Surface Wiring, Concealed Wiring

Plumbing System

Water supply and drainage network.

Supplies clean water and removes wastewater.

Pipes, Valves, Fittings, Water Tanks

UPVC, CPVC, PPR, GI

HVAC System

Heating, Ventilation, and Air Conditioning setup.

Regulates indoor temperature, humidity, and air quality.

Ducts, Vents, Compressors

Split AC, Centralized, VRF

Fire Safety System

Fire prevention and suppression system.

Detects and controls fires, ensuring safety.

Fire Extinguishers, Sprinklers, Smoke Detectors

Manual, Automatic

Paint & Finishing

Coating applied to walls, ceilings, and other surfaces.

Enhances aesthetics and protects surfaces from damage.

Primer, Paint, Putty

Water-Based, Oil-Based, Textured